The CLUG project is structured in five work packages. Each one of them will be subject to many deliverables. You will find below the deliverables in their final status.

Deliverable Number Title Description Dissemination Level Due Date
Dissemination Plan
D2.1 High Level Mission Requirements Definition

Public document with the definition of the high level mission requirements that are the basis for the deviation of high level system requirements.

Public 30 Nov 2020
D2.2 Operational Scenarios Definition

Public document with the definition of scenarios of railway operation, relevant for the project.

Public 30 Nov 2020
D2.7 Identified Validation Certification Methods

D2.7 identifies the most suitable methods for validation and certification considering work from WP2.3, WP 2.6 and WP2.7 and taking into account the legal background. D2.7 is the main input for D5.10 the prototypical certification.

Public 31 May 2021
D4.3 Ground Truth

The ground truth (true position of the train) generated for the individual test runs will be delivered in an agreed format, supplemented by a description on how the ground truth has been generated. This will allow the involved parties to re-evaluate the collected raw data at a later stage against the true position of the train.

Public 31 May 2021
D5.3 Project brochure

Public project brochure.

Public 31 May 2021
D5.4 Definition of the Required maps for Localisation

It defines, according of the results of the different WPs, a comprehensive definition of the digital map for the train localisation system

Public 30 Nov 2021
D5.6 Final Dissemination Report

The report presents the project communication and dissemination activities’ results.

Public 30 Nov 2021
D5.7 Preliminary Definition of the System Performances and Interfaces

It provides :
- the mission definition and requirements for a train localisation unit;
- the preliminary definition of Failsafe multi-sensor localisation (system, sub system, internal and potential external interfaces);
- the feasibility (performances and assessed safety of life level) of Failsafe multi-sensor localisation unit.

Public 30 Nov 2021
WP 5 - Application to the Train Evaluation System

Dissemination Plan

April 30, 2020